Promised vs. Produced Tracker · Arizona · as of Q3 2026

Arizona has been promised 6 factories since 2017. 2 are producing.

4th of 33 states by announced capital · 8th of 17 by share producing, among states with three or more promises

6 promises · $38B announced · 2 producing · 3 not yet producing · 1 cancelled or closed

Intel Fab 52 & Fab 62 (Ocotillo, Chandler AZ) · $20.0B · ProducingTSMC Fab 21 Phoenix · $12.0B · ProducingAmkor Peoria Advanced Packaging Facility · $2.0B · Under constructionLG Energy Solution Arizona Battery Complex (Queen Creek) · $1.4B · Under constructionKORE Power KOREPlex Battery Cell Gigafactory (Buckeye, AZ) · $1.2B · CancelledAmerican Battery Factory Tucson Gigafactory · $1.2B · Under constructionTSMC Fab 21 PhoenixAmkor Peoria Advanced Packagi…KORE Power KOREPlex Battery C…Intel Fab 52 & Fab 62 (Ocotil…LG Energy Solution Arizona Ba…American Battery Factory Tucs…
producing not yet producing cancelled or closedmark area · announced capitalSites placed at the town · the largest promises are named · a mark opens its row

Arizona, promise by promise

Largest announced capital first. Each row links to its announcement and to the source for its latest status.

announcement to promised first output past the promised date, not producing producing × promise cancelled or closed
  1. Intel Fab 52 & Fab 62 (Ocotillo, Chandler AZ)

    Semiconductors · AZ

    $20.0B · 3,000 jobs · announced Mar 2021 · promised 2024 · first output 2025-10

    sources · promise intc.com · status datacenterdynamics.com

    Wrong? Correct it on GitHub or email us

    Producing1y 3m late
  2. TSMC Fab 21 Phoenix

    Semiconductors · AZ

    $12.0B · 1,600 jobs · announced May 2020 · promised 2024 · first output 2024 (second half)

    sources · promise pr.tsmc.com · status aztechcouncil.org

    Wrong? Correct it on GitHub or email us

    Producingon time
  3. Amkor Peoria Advanced Packaging Facility

    Semiconductors · AZ

    $2.0B · 2,000 jobs · announced Dec 2023 · promised 2026 · first output: not yet

    sources · promise areadevelopment.com · status constructiondive.com

    Wrong? Correct it on GitHub or email us

    Under construction3m past promise
  4. LG Energy Solution Arizona Battery Complex (Queen Creek)

    Battery · AZ

    $1.4B · jobs unconfirmed · announced Mar 2022 · promised 2024 · first output: not yet

    sources · promise azcommerce.com · status abc15.com

    Wrong? Correct it on GitHub or email us

    Under construction2y 3m past promise
  5. KORE Power KOREPlex Battery Cell Gigafactory (Buckeye, AZ)

    Battery · AZ

    $1.2B · 3,000 jobs · announced Jul 2021 · promised 2023-Q2 · first output: none, cancelled

    sources · promise americanprogress.org · status manufacturingdive.com

    Wrong? Correct it on GitHub or email us

    Cancelledoriginal promise not kept
  6. American Battery Factory Tucson Gigafactory

    Battery · AZ

    $1.2B · 1,000 jobs · announced Dec 2022 · no promised date · first output: not yet

    sources · promise prnewswire.com · status currentcells.com

    Wrong? Correct it on GitHub or email us

    Under constructionno promised date on record

Dates follow the announcement's own precision: a year with no month is drawn at mid-year, a quarter at its middle month. A person has checked every figure here against its sources, and every check is public. We log every correction made after publication, with its reason.

Other states: Texas New York Louisiana North Carolina Georgia Ohio Michigan Virginia Indiana Tennessee Idaho Iowa Kentucky Alabama Wisconsin South Carolina Utah Pennsylvania Kansas California Oklahoma Illinois Nevada New Mexico Arkansas Mississippi West Virginia Oregon South Dakota Montana Delaware Nebraska

The next recount

Get the recount when we publish it.

We recount every promise each quarter. The next one is due at the end of Q4 2026.

How we collected this
Data: Promised vs. Produced Tracker, 165 promises at the $1B or 2,000 direct jobs floor across 33 states, verified through 2026-10-03 · A person verified every promise against its sources, and we have logged 88 corrections · 165 of 165 carry both a promise source and a status source · map: Census cartographic boundaries via us-atlas, AlbersUSA · We placed each site at its town by hand and drew the bars and marks from the Tracker, without a chart library